Hello to our Bright Beginnings families and friends!
We are so excited to share construction updates with you! As many of you know our Forest Lakes locations
renovations are now underway. Below you will find a list of things that occurred this weekend as well as
things to expect in the upcoming week! Take a look at our pictures to see our incredible progress!
This past weekend and upcoming week endeavors:
- Last week we had 14-security camera system set-up and is now running! (Cameras are for security
and training purposes only. We respect all students and teachers privacy.)
- New interior window cutouts for classrooms – Glass will be installed after painting.
- New flooring started – this should be completed by the end of the week! (They’re fantastic!)
- New toilets installed by end of the week.
- Painting prep will begin this week!
- New cabinets for entire building will be arriving Tuesday! Installation starts Wednesday!! (Who
doesn’t love storage, right!?)
- Lobby refurbished and window added to our Director office.
- All 3 building locations were washed with DNA soft clean to ensure no molding.
WOW! So much happening, and more to come! Stay tuned for more updates. We are still on schedule for
total completion at Forest Lakes on July 10!!
Important Reminders:
- Ms. PJ is away this week on vacation. Ms. Alison (Me!) will be greeting our Forest Lakes families each
morning. Feel free to stop by and say Hello!
- As you will see in the AMAZING pictures below, cubbies are no longer in the hallway. Cubbies will be on the
floor in each classroom until they are installed.